Implementation progress at Nhon Depot, line 3, Nhon – Hanoi Station section

79431317 3439751496065095 6933271646149017600 n

79781723 3439751266065118 2146401930421731328 n

80029021 3439752209398357 3858814999178772480 n

The construction of Nhon Depot belongs to construction package CP05 – Architectural works at Depot. This package consists of 21 key components in Operations Control Center (OCC) and workshops. At present, OCC construction and tile components are complete. Besides, the project has completed concrete and steel structures for eight workshops and is building three workshops and three electrical houses.

(Hanoi Metro Railway)